Click below for further details of the Boathouse Project

 

Latest Work

 

Bay 1 (Roadside)

Currently Bay 1 is being used to house  boats for repair. The next work planned for this bay is to seal the floor and paint the roadside wall.  One half of this bay will be for changing and showers etc whereas the down-river end will be for housing small boats.

 

 

Bay 2 (Centre)

The wall against bay 3 has been painted and the floor completed pending the application of non-slip paint. Ergo-meters are stored here. A further consideration for this bay is racking for boats.

 

 

Bay 3 (Riverside)

 The roof has been sealed against condensation, the internal wall painted and the walls clad. The steel uprights have been clad and skirting board is being added. Focus is now centred on the ramps and balcony . 

 

 

Ramps and Balcony

Work to the ramps is proceeding very quickly and the balcony is taking shape.

    Work in Progress

    

 

                Messrs John & Ted Hills                                             General view of Bay 3

         Measuring up and fitting skirting board.

  

Above - Upriver entrance ramp

  

                                               Above - The Balcony with storage area below

 

   

Latest exterior views - Friday 20th June 2008